List of questions
Related questions
Question 98 - PSPO-I discussion
When does the next Sprint begin?
(choose the best answer)
A.
The Monday following the Sprint Review.
B.
Immediately after the conclusion of the previous Sprint.
C.
Immediately following the next Sprint Planning.
D.
When the Product Owner is ready.
Your answer:
0 comments
Sorted by
Leave a comment first