Question 112 - PSPO-I discussion
Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
A.
Make up a plan for the rest of the project.
B.
Define the major product features and a release plan architecture.
C.
Analyze, describe, and document the requirements for the subsequent Sprints.
D.
Build at least one piece of valuable functionality.
E.
Create at least one valuable, useful Increment.