True or False: The Scrum Team is accountable for creating a valuable increment every Sprint.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: A

Explanation:

The Scrum Team is accountable for creating a valuable increment every Sprint. The Increment is the sum of all Product Backlog items Done during a Sprint and the value of all the previous Increments. The entire Scrum Team is accountable for creating a valuable and useful Increment every Sprint1. The Product Owner is responsible for maximizing the value of the product resulting from the work of the Scrum Team1. The Developers are responsible for creating a Done Increment that meets the Sprint Goal1. The Scrum Master is responsible for establishing Scrum as defined in the Scrum Guide and helping everyone understand Scrum theory, practices, rules, and values1.

Scrum Guide

What is an Increment and how Does it Connect with the other Elements of Scrum?

The Professional Product Owner

asked 23/09/2024
Khalfan KAABI
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first