Question 123 - PSPO-I discussion
When does the second Sprint start?
(choose the best answer)
A.
After the customer completes acceptance testing of the first Sprint.
B.
Once the architectural changes for the second Sprint are approved by the senior architect.
C.
Immediately after the first Sprint.
D.
After the Product Backlog items for the second Sprint have been selected.
Your answer: