ExamGecko
Home / IIBA / CCBA / Practice Test 7
Ask Question

IIBA CCBA Practice Test 7

00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Risk management plan
Risk management plan
Stakeholder register
Stakeholder register
Project scope statement
Project scope statement
Risk register
Risk register
Comment (0)
Suggested answer: B
Explanation:

You would not need the stakeholder register to perform qualitative risk analysis. Qualitative Risk

Analysis uses the likelihood and impact of the identified risks in a fast and cost-effective manner.

Qualitative Risk Analysis establishes a basis for a focused quantitative analysis or Risk Response Plan by evaluating the precedence of risks with a concern to impact on the project's scope, cost, schedule, and quality objectives.

The qualitative risk analysis is conducted at any point in a project life cycle. The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical response. The inputs to the Qualitative Risk Analysis process are:

Organizational process assets Project Scope Statement Risk Management Plan Risk Register

asked 18/09/2024
Oscar Ballabriga
35 questions