A platform engineer is connecting a new Dell EMC PowerScale F600 node to the back-end switch.

How should the back-end cable be connected?

A.

From PCIe slot 3 to the back-end InfiniBand switch.

A.

From PCIe slot 3 to the back-end InfiniBand switch.

Answers
B.

From PCIe slot 1 to the back-end Ethernet switch.

B.

From PCIe slot 1 to the back-end Ethernet switch.

Answers
C.

From PCIe slot 1 to the back-end InfiniBand switch.

C.

From PCIe slot 1 to the back-end InfiniBand switch.

Answers
D.

From PCIe slot 3 to the back-end Ethernet switch.

D.

From PCIe slot 3 to the back-end Ethernet switch.

Answers
Suggested answer: B

Explanation:

For Dell EMC PowerScale F600 nodes, back-end connectivity is essential for node communication and cluster operations. The F600 uses Ethernet for back-end networking.

Cabling Instructions:

PCIe Slot 1 Usage:

PCIe slot 1 is designated for back-end Ethernet connections in F600 nodes.

This slot houses the network interface card (NIC) responsible for internal cluster communication.

Connecting to Back-End Ethernet Switch:

Cables from PCIe slot 1 should be connected to the back-end Ethernet switch.

Ensures that nodes can communicate over the internal network.

Key Points:

Avoiding InfiniBand

Reference:

F600 nodes use Ethernet, not InfiniBand, for back-end networking.

Options mentioning InfiniBand switches are incorrect.

Slot Selection:

PCIe slot 3 is not used for back-end connections in F600 nodes.

Correct slot usage is critical for network functionality.

Dell PowerScale Reference:

Dell EMC PowerScale Hardware Installation Guide:

Cabling Diagrams for F600 Nodes illustrate the correct connections from PCIe slot 1.

Back-End Network Setup section provides detailed instructions.

Networking Best Practices:

Use recommended cables and connectors for Ethernet connections.

Label cables and ports to prevent misconfiguration.

A Dell EMC PowerScale platform engineer is asked to reimage a node.

What should they check before they start the reimage process?

A.

The treedelete job has been run against the node.

A.

The treedelete job has been run against the node.

Answers
B.

Customer has redundant paths to their data.

B.

Customer has redundant paths to their data.

Answers
C.

Node has been SmartFailed and removed from the cluster.

C.

Node has been SmartFailed and removed from the cluster.

Answers
D.

SyncIQ job has been run to copy the node data.

D.

SyncIQ job has been run to copy the node data.

Answers
Suggested answer: C

Explanation:

Reimaging a node in a Dell EMC PowerScale cluster is a significant operation that requires careful preparation to prevent data loss and maintain cluster integrity.

Pre-Reimage Checklist:

SmartFail the Node:

Initiate a SmartFail process to evacuate data from the node to other nodes in the cluster.

Ensures that no data is lost during the reimage process.

Remove Node from Cluster:

After SmartFailing, the node should be properly removed from the cluster configuration.

Prevents cluster confusion and potential conflicts.

Key Points:

Data Protection:

SmartFailing redistributes data, maintaining data protection policies.

Critical for clusters that do not have full data redundancy.

Operational Readiness:

Verify that the cluster is healthy before proceeding.

Check that there are sufficient resources to accommodate data migration.

Dell PowerScale

Reference:

Dell EMC PowerScale OneFS Administration Guide:

Chapter on Node Removal and Replacement outlines the steps for SmartFailing and reimaging.

Data Protection Considerations emphasizes the importance of SmartFailing.

Best Practices:

Monitor the SmartFail process to completion before starting reimage.

Communicate with stakeholders about potential performance impacts during data evacuation.

What is a precaution when working with Dell EMC PowerScale equipment?

A.

Nodes can operate above 40 degrees C, but only for limited periods of time.

A.

Nodes can operate above 40 degrees C, but only for limited periods of time.

Answers
B.

Connections to the branch circuit need not be properly grounded.

B.

Connections to the branch circuit need not be properly grounded.

Answers
C.

Use side stabilizers if the rack is not securely bolted to the floor.

C.

Use side stabilizers if the rack is not securely bolted to the floor.

Answers
D.

The total rack load should not exceed 70% of the branch circuit rating.

D.

The total rack load should not exceed 70% of the branch circuit rating.

Answers
Suggested answer: C

Explanation:

When working with Dell EMC PowerScale equipment, safety precautions are essential to prevent equipment damage and personal injury. One critical precaution is ensuring that the equipment racks are stable to prevent tipping hazards.

Key Points:

Use of Side Stabilizers:

If the rack is not securely bolted to the floor, side stabilizers must be used.

Side stabilizers provide additional support and prevent the rack from tipping over during installation or maintenance activities.

This is especially important when equipment is being added or removed from the rack, which can shift the center of gravity.

Rack Stability:

Proper rack installation involves securely bolting the rack to the floor or using stabilizing devices.

Unstable racks pose a significant risk to personnel and equipment.

Safety Compliance:

Following the manufacturer's guidelines ensures compliance with safety regulations and standards.

Prevents accidents that could result in injury or damage.

Dell PowerScale

Reference:

Dell EMC PowerScale Hardware Installation Guide:

Chapter on Rack Installation:

Recommends that if racks are not bolted to the floor, side stabilizers should be installed.

Provides detailed instructions on installing side stabilizers.

Safety Precautions:

Emphasizes the importance of rack stability during equipment installation and maintenance.

Best Practices:

Always verify that racks are secure before performing any work.

Use appropriate personal protective equipment (PPE) when working with heavy equipment.

Follow all safety warnings and cautions provided by Dell EMC.

A PowerScale customer is planning to expand a Dell EMC PowerScale Gen 5 cluster with H500 nodes.

What is a consideration?

A.

Minimum of three Gen 6 nodes are needed.

A.

Minimum of three Gen 6 nodes are needed.

Answers
B.

Backend is not supported.

B.

Backend is not supported.

Answers
C.

Only Gen 5 nodes can be added to the cluster.

C.

Only Gen 5 nodes can be added to the cluster.

Answers
D.

Minimum of four H500 nodes are needed.

D.

Minimum of four H500 nodes are needed.

Answers
Suggested answer: A

Explanation:

When expanding a Dell EMC PowerScale Gen 5 cluster with Gen 6 nodes, such as the H500, certain requirements and considerations must be taken into account.

Key Points:

Minimum Node Requirement:

A minimum of three Gen 6 nodes is required to add to an existing Gen 5 cluster.

This is necessary to form a separate node pool within the cluster that maintains compatibility and optimal performance.

Compatibility Considerations:

Gen 6 nodes can be added to a Gen 5 cluster, but they must be added in groups of at least three nodes.

This ensures that the new nodes can participate fully in the cluster's operations and data protection schemes.

Node Pools:

The cluster will have separate node pools for Gen 5 and Gen 6 nodes.

Data can be moved or balanced between node pools according to policies and performance requirements.

Dell PowerScale

Reference:

Dell EMC PowerScale OneFS Administration Guide:

Chapter on Cluster Expansion:

Discusses adding new nodes to an existing cluster and the requirements for different generations.

States the minimum number of nodes required when adding Gen 6 nodes to a Gen 5 cluster.

Dell EMC PowerScale Best Practices Guide:

Node Compatibility and Mixing:

Provides guidelines on mixing node generations within a cluster.

Recommends adding at least three nodes of the new generation.

Considerations:

Option B is incorrect because back-end support is available.

Option C is incorrect because Gen 6 nodes can be added to a Gen 5 cluster.

Option D is incorrect because the minimum required is three, not four.

When a platform engineer disconnects and removes the power supply from a Dell EMC PowerScale Gen 6 node, they see an LED on the inside of the compute module.

What does the LED indicate?

A.

Power supply was not removed correctly and the node is shutting down.

A.

Power supply was not removed correctly and the node is shutting down.

Answers
B.

Platform engineer has exactly two minutes to swap the power supply.

B.

Platform engineer has exactly two minutes to swap the power supply.

Answers
C.

Visible LED is from the front panel of the node.

C.

Visible LED is from the front panel of the node.

Answers
D.

Pair node is supplying redundant power.

D.

Pair node is supplying redundant power.

Answers
Suggested answer: D

Explanation:

In Dell EMC PowerScale Gen 6 nodes, such as the ones in the F-series, nodes are deployed in pairs within a chassis, sharing power supplies for redundancy.

Key Points:

LED Indicator Inside Compute Module:

When a power supply is removed from one node, an LED inside the compute module may illuminate.

This LED indicates that the node is still receiving power from its pair node's power supply, ensuring continuous operation.

Redundant Power Supply:

PowerScale Gen 6 nodes are designed with redundant power configurations.

If one power supply fails or is removed, the paired node's power supply provides power to both nodes.

Safe Removal and Replacement:

The LED serves as a visual indicator that the node is still powered, and caution should be exercised when handling components.

There is no immediate shutdown or time limit for replacing the power supply due to the redundancy.

Dell PowerScale

Reference:

Dell EMC PowerScale Hardware Installation Guide:

Chapter on Power Supply Replacement:

Explains the redundant power features and the role of the pairing between nodes.

Provides instructions on safely removing and replacing power supplies.

Visual Indicators:

Details the meaning of LEDs within the compute module.

Confirms that an illuminated LED in this context indicates redundant power from the pair node.

Best Practices:

Always verify the node's power status before performing maintenance.

Use the proper procedures to remove and replace hardware components to prevent damage.

What should the platform engineer do to retain critical information when replacing a system board on a Dell EMC PowerScale F200 node?

A.

Run isi_node_restore -force

A.

Run isi_node_restore -force

Answers
B.

Flash the BIOS

B.

Flash the BIOS

Answers
C.

Reinstall the PowerScale license

C.

Reinstall the PowerScale license

Answers
D.

Run EasyRestore

D.

Run EasyRestore

Answers
Suggested answer: D

Explanation:

When replacing a system board (motherboard) on a Dell EMC PowerScale F200 node, critical system information such as the node's identity, network configuration, and cluster membership must be preserved.

Key Points:

EasyRestore Utility:

EasyRestore is a utility provided by Dell EMC to restore critical node information after hardware replacements like system boards.

It automates the process of restoring the node's identity and configuration without manual intervention.

Retention of Critical Information:

Running EasyRestore ensures that the node re-integrates into the cluster with the correct settings.

It restores the node's serial number, GUID, and other essential identifiers.

Procedure After System Board Replacement:

After physically replacing the system board, the platform engineer should boot the node and run EasyRestore.

This process retrieves the necessary information from the node's backup flash storage.

Dell PowerScale

Reference:

Dell EMC PowerScale OneFS Administration Guide:

Chapter on Hardware Replacement Procedures:

Describes the steps to replace a system board and the importance of running EasyRestore afterward.

Details how EasyRestore works and what information it restores.

Technical Advisories:

Emphasize that failure to run EasyRestore may result in the node not functioning correctly within the cluster.

Incorrect Options:

Option A (isi_node_restore -force) is not the correct utility for this task.

Option B (Flash the BIOS) is unnecessary as the BIOS is part of the system board.

Option C (Reinstall the PowerScale license) is not required because licensing is managed at the cluster level, not per node.

What is the purpose of SolVe Desktop?

A.

Gather logs from the cluster for analysis

A.

Gather logs from the cluster for analysis

Answers
B.

Perform pre-upgrade checks on the cluster

B.

Perform pre-upgrade checks on the cluster

Answers
C.

Provide centralized access to step-by-step procedures

C.

Provide centralized access to step-by-step procedures

Answers
D.

Provide access to the latest OneFS codes and firmware upgrades

D.

Provide access to the latest OneFS codes and firmware upgrades

Answers
Suggested answer: C

Explanation:

SolVe Desktop is a tool provided by Dell EMC that offers a centralized platform for accessing detailed, step-by-step procedures for servicing and maintaining Dell EMC equipment, including PowerScale systems.

Key Points:

Purpose of SolVe Desktop:

Acts as a comprehensive resource for service personnel.

Provides guided procedures for installation, maintenance, upgrades, and troubleshooting.

Features:

Interactive and customizable workflows.

Up-to-date documentation and best practices.

Access to knowledge base articles and technical advisories.

Benefits:

Ensures that engineers follow the correct procedures.

Reduces the risk of errors during service activities.

Enhances efficiency and effectiveness of maintenance tasks.

Dell PowerScale

Reference:

SolVe Desktop User Guide:

Outlines the functionalities and how to use the tool effectively.

Emphasizes its role in providing access to step-by-step procedures.

Dell EMC Support Resources:

Encourages service personnel to utilize SolVe Desktop for accurate and approved methods.

Incorrect Options:

Option A (Gather logs from the cluster for analysis) is not the primary function of SolVe Desktop.

Option B (Perform pre-upgrade checks on the cluster) is a function of other tools like OneFS Upgrade Advisor.

Option D (Provide access to the latest OneFS codes and firmware upgrades) is handled through Dell EMC support portals.

Which resource provides up-to-date instructions to service a Dell EMC PowerScale system?

A.

Dell Quick Reference Guide

A.

Dell Quick Reference Guide

Answers
B.

Dell Enterprise Configuration Services

B.

Dell Enterprise Configuration Services

Answers
C.

Dell SolVe Online

C.

Dell SolVe Online

Answers
D.

Dell iDRAC Service Module

D.

Dell iDRAC Service Module

Answers
Suggested answer: C

Explanation:

Dell SolVe Online (and SolVe Desktop) is the primary resource for obtaining up-to-date, detailed service procedures for Dell EMC PowerScale systems.

Key Points:

Purpose of Dell SolVe Online:

Provides the latest service procedures, including installation, replacement, and troubleshooting guides.

Ensures that technicians have access to current and accurate information.

Features:

Interactive procedures with step-by-step instructions.

Customizable checklists and workflows.

Regularly updated content reflecting the latest product updates and best practices.

Accessibility:

Available online and as a downloadable application (SolVe Desktop).

Requires authentication to ensure that only authorized personnel access sensitive service information.

Dell PowerScale

Reference:

Dell EMC Support Resources:

Directs service personnel to use SolVe Online for official procedures.

Emphasizes the importance of using approved resources to maintain product integrity and support agreements.

Incorrect Options:

Option A (Dell Quick Reference Guide) provides summary information but not detailed service procedures.

Option B (Dell Enterprise Configuration Services) is a professional service offering, not a resource for procedures.

Option D (Dell iDRAC Service Module) is a management tool for servers, not for accessing service instructions for PowerScale systems.

A platform engineer has connected to a Dell EMC PowerScale F600 node using a serial connection. The session is unresponsive.

What action should the engineer take?

A.

Enable the serial port from the front panel menu

A.

Enable the serial port from the front panel menu

Answers
B.

Connect to the primary node of the pair

B.

Connect to the primary node of the pair

Answers
C.

Configure the cluster before connecting to the node

C.

Configure the cluster before connecting to the node

Answers
D.

Check the settings of the serial connection

D.

Check the settings of the serial connection

Answers
Suggested answer: D

Explanation:

When connecting to a Dell EMC PowerScale F600 node via a serial connection and the session is unresponsive, the most common issue is incorrect serial connection settings.

Key Points:

Serial Connection Settings:

The serial console requires specific settings to communicate properly:

Baud rate: 115200

Data bits: 8

Parity: None

Stop bits: 1

Flow control: None

Incorrect settings will result in an unresponsive or garbled session.

Troubleshooting Steps:

Verify that the serial connection parameters match the required settings.

Ensure that the correct serial port is being used.

Check the physical connection for loose cables or faulty adapters.

Other Considerations:

The serial port on the node does not need to be enabled from the front panel.

Connecting to the primary node or configuring the cluster is not necessary for serial console access.

Dell PowerScale

Reference:

Dell EMC PowerScale Hardware Installation Guide:

Appendix on Console Access:

Provides the correct serial connection settings for accessing the node console.

Offers troubleshooting tips for common connection issues.

Best Practices:

Use reliable serial communication software (e.g., PuTTY, Tera Term).

Confirm that the serial cable and any USB-to-serial adapters are functioning properly.

The SSD has failed in a Dell EMC PowerScale H400 node that has one SSD installed. A technician is asked to replace it.

Where should the new drive be installed?

A.

Left slot at the back of the node

A.

Left slot at the back of the node

Answers
B.

Position 0 and sled A

B.

Position 0 and sled A

Answers
C.

Position 0 and sled E

C.

Position 0 and sled E

Answers
D.

Right slot at the back of the node

D.

Right slot at the back of the node

Answers
Suggested answer: C

Explanation:

In a Dell EMC PowerScale H400 node that has one SSD installed and requires replacement, the new SSD should be installed in the correct slot to ensure proper operation.

Key Points:

SSD Slot Location:

The H400 node uses sleds for drive placement.

SSDs are installed in specific positions to support metadata acceleration and caching functions.

Position 0 and sled E is designated for the SSD in an H400 node.

Drive Replacement Procedure:

Identify the correct sled and position for the SSD.

Power down the node if necessary, following safety procedures.

Remove the faulty SSD and install the new SSD in the correct slot.

Importance of Correct Placement:

Installing the SSD in the wrong slot can lead to the node not recognizing the drive.

May affect the performance and data protection features of the cluster.

Dell PowerScale

Reference:

Dell EMC PowerScale Hardware Replacement Guide:

Section on SSD Replacement for H400 Nodes:

Specifies that the SSD should be installed in Position 0 of sled E.

Provides diagrams and step-by-step instructions.

Node Documentation:

Illustrates the drive bay numbering and sled identification.

Emphasizes the importance of installing drives in the correct positions.

Incorrect Options:

Option A (Left slot at the back of the node) and Option D (Right slot at the back of the node) do not correspond to the correct SSD slot.

Option B (Position 0 and sled A) is not the designated slot for the SSD in an H400 node.

Total 101 questions
Go to page: of 11