Nutanix NCS-Core Practice Test - Questions Answers, Page 18
List of questions
Related questions
A consultant is preparing to add new nodes into an existing cluster. The current cluster AOS version is 5.8. The new expansion node is currently running AOS 5.9 code. The cluster must continue to run at its current AOS version.
Which method can be used to successfully add the node?
While trying to upgrade AOS in a cluster, a consultant receives a warning message that there are two powered-on VMs that need to be powered off for the upgrade to proceed.
What would cause this warning to be issued?
A consultant successfully completes a Foundation using a flat switch. The consultant then works with the customer to move the cluster over to their production network. After the move, the CVMs and hypervisors can no longer communicate, which prevents the cluster from starting.
Which option should be used to resolve this issue?
A customer racks all nodes in the new cluster. The customer does not allow IPv6 for node discovery.
The consultant is not allowed to use the consultant's own flat switch in the customer's environment.
Which step should the consultant take to resolve this issue?
A consultant configures a Nutanix cluster and integrates the hosts into vCenter using VMware best practices. The customer has requested that the Nutanix cluster only have a single datastore.
Upon configuring the cluster per the customer requirements, vCenter displays an alert regarding the heartbeat datastore. The consultant adds the das.ignoreInsufficientHbDatastore value = true rule. The container can be seen from each host, but the alert remains active.
What should the consultant do to resolve this issue?
After finishing foundation on an AHV cluster, a consultant is preparing to plug into the customer network given the following set of requirements:
* All network traffic on trunks is tagged
* Customer is using LACP
* A native VLAN is not in use
Which set of commands should the consultant use to ensure cluster connectivity on customer equipment?
After installation, network ports are properly configured with the default active-backup bonding.
One 10GbE port goes to switch 1. Another 10GbE port goes to switch 2. A consultant tests failover by manually pulling one of the cables and notices it is taking too much time to failover, which is causing excessive packet loss.
What should the consultant enable to resolve this issue?
A consultant creates a new cluster using ESXi as the hypervisor. After creating the cluster, the consultant begins to run Life Cycle Manager (LCM) updates. During the LCM upgrade pre-checks, an error is returned.
Which configuration is causing this issue?
A customer has engaged a Nutanix consultant to deploy a cluster consisting of two NX-3460-G6 blocks. The consultant arrives at the customer site and fines the following:
* One rack with a total of 5U available
* Two ToR switches with 14 total available ports
* Dual PDUs with six available sockets
What will prevent the consultant from successfully installing the cluster?
During a six-node cluster deployment, one node fails to image successfully and Foundation is unable to automatically configure the cluster. The consultant decides to manually complete cluster formation with the successful nodes, then expand the cluster with the remaining unconfigured node.
Which command should be used to begin the process?
Question