You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

A.
Final program audit report
Answers
A.
Final program audit report
B.
Audit of program financials
Answers
B.
Audit of program financials
C.
Lessons learned documentation
Answers
C.
Lessons learned documentation
D.
Certificate of program completion
Answers
D.
Certificate of program completion
Suggested answer: D