Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

A.
Stakeholder management plan
Answers
A.
Stakeholder management plan
B.
Communications management plan
Answers
B.
Communications management plan
C.
Human resource management plan
Answers
C.
Human resource management plan
D.
Interface management plan
Answers
D.
Interface management plan
Suggested answer: D