Robert is the program manager for his organization which operates in a matrix structure.

Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should

Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

A.
Resource management plan
Answers
A.
Resource management plan
B.
Program management calendar
Answers
B.
Program management calendar
C.
Schedule management plan
Answers
C.
Schedule management plan
D.
Resource calendar
Answers
D.
Resource calendar
Suggested answer: A