Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?
A.
These are for Julie's reference when she is reviewed by the project sponsor.
B.
These are given to the project sponsor so he can review the project.
C.
These are given to the project steering committee so they may review the project performance.
D.
These are transferred to the lessons learned knowledge base.