Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

A.
Deadlines for project milestones
Answers
A.
Deadlines for project milestones
B.
Building codes
Answers
B.
Building codes
C.
A predetermined program budget
Answers
C.
A predetermined program budget
D.
Weather
Answers
D.
Weather
Suggested answer: D