A project manager in your program is using progress elaboration as part of their planning approach. This approach is also known as what planning methodology?

A.
Waterfall management
Answers
A.
Waterfall management
B.
Rolling wave planning
Answers
B.
Rolling wave planning
C.
Scope refinements
Answers
C.
Scope refinements
D.
Incremental planning
Answers
D.
Incremental planning
Suggested answer: B