Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

A.
Risk management plan
Answers
A.
Risk management plan
B.
Risk register
Answers
B.
Risk register
C.
Activity list
Answers
C.
Activity list
D.
Activity list and attributes
Answers
D.
Activity list and attributes
Suggested answer: D