Question 228 - PgMP discussion
You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?
A.
Preventive action
B.
Corrective action
C.
Gold plating
D.
Program scope change