You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

A.
Preventive action
Answers
A.
Preventive action
B.
Corrective action
Answers
B.
Corrective action
C.
Gold plating
Answers
C.
Gold plating
D.
Program scope change
Answers
D.
Program scope change
Suggested answer: D