You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?
A.
Give it to the client for his information.
B.
Destroy it, as this information is relevant to the client.
C.
Archive it as part of your organization's process assets.
D.
Leave it as is for the client to destroy or archive.