Question 243 - PgMP discussion
A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?
A.
Negative stakeholder
B.
Positive stakeholder
C.
Key stakeholder
D.
Hurdle stakeholder