What does CPI value less than 1.0 indicates?

A.
Cost overrun for work completed
Answers
A.
Cost overrun for work completed
B.
Scheduled performance is great
Answers
B.
Scheduled performance is great
C.
Cost underrun of performance to date
Answers
C.
Cost underrun of performance to date
D.
Cost for completed work is as per estimate
Answers
D.
Cost for completed work is as per estimate
Suggested answer: A