Which of the following shows the ratio between a task's budgeted and actual costs?

A.
To-Complete Performance Index (TCPI)
Answers
A.
To-Complete Performance Index (TCPI)
B.
Schedule Variance (SV)
Answers
B.
Schedule Variance (SV)
C.
Schedule Performance Index (SPI)
Answers
C.
Schedule Performance Index (SPI)
D.
Cost Performance Index (CPI)
Answers
D.
Cost Performance Index (CPI)
Suggested answer: D