Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

A.
Fast tracking
Answers
A.
Fast tracking
B.
Compressing
Answers
B.
Compressing
C.
Float
Answers
C.
Float
D.
Crashing
Answers
D.
Crashing
Suggested answer: A