You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

A.
.83
Answers
A.
.83
B.
-$20,000
Answers
B.
-$20,000
C.
.91
Answers
C.
.91
D.
Negative ten percent
Answers
D.
Negative ten percent
Suggested answer: C