An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future, similar situations?
A.
Accept the risk
B.
Seek an expert opinion
C.
Establish an on-call risk response team
D.
Review the risk severity matrix