A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.

At the next stakeholder meeting, what should the program manager present to address their concerns?

A.
Program charter
Answers
A.
Program charter
B.
Program scope assessment results
Answers
B.
Program scope assessment results
C.
Business case and program roadmap
Answers
C.
Business case and program roadmap
D.
Expected program benefits management plan
Answers
D.
Expected program benefits management plan
Suggested answer: D