The program manager must define the program and understand the organization's target market and customer needs. What should the program manager do first?

A.
Brainstorm with the program team to decide on the definitions of the target market.
Answers
A.
Brainstorm with the program team to decide on the definitions of the target market.
B.
Meet with peers to identify the company's competitors in the target market.
Answers
B.
Meet with peers to identify the company's competitors in the target market.
C.
Meet with the project managers to identify the target market.
Answers
C.
Meet with the project managers to identify the target market.
D.
Work with the program sponsor to assess the needs of the target market.
Answers
D.
Work with the program sponsor to assess the needs of the target market.
Suggested answer: A