Question 291 - PgMP discussion
What actions are taken in the process of developing and maintaining a program risk register?
A.
Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and provide the foundation for the risk management plan.
B.
Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify the root cause of potential risks.
C.
Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and proactively manage program issues.
D.
Assign ownership of risks with appropriate responsibilities, document agreed-upon response strategies, and identify residual risks.