List of questions
Related questions
Question 299 - PgMP discussion
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?
A.
Certify contract completion
B.
Conduct a procurement audit to review the procurement process
C.
Assess all contracts to ensure all agreed conditions are met
D.
Review contract management plan for completeness
Your answer: