A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?

A.
Certify contract completion
Answers
A.
Certify contract completion
B.
Conduct a procurement audit to review the procurement process
Answers
B.
Conduct a procurement audit to review the procurement process
C.
Assess all contracts to ensure all agreed conditions are met
Answers
C.
Assess all contracts to ensure all agreed conditions are met
D.
Review contract management plan for completeness
Answers
D.
Review contract management plan for completeness
Suggested answer: C