Question 301 - PgMP discussion
The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee.
What do the current findings show?
A.
Project C is running behind schedule and is over budget; projects A, B, and D are on schedule.
B.
Project A is running ahead of schedule and is under budget; projects B, C, and D are behind schedule.
C.
The overall program is performing within an acceptable level of variance.
D.
Project A is running behind schedule and is over budget; projects B, C, and D are on schedule.