Question 305 - PgMP discussion

Report
Export

An R&D group director approves a major program's charter. Although the director has a high level of understanding of the program's scope, they are unsure of how the program manager can be successful in delivering the program's commitments.

What should the program manager do to align stakeholders with planning and monitoring the program's progress?

A.
Establish high-level program milestones
Answers
A.
Establish high-level program milestones
B.
Develop an accountability matrix, and assign program roles and responsibilities
Answers
B.
Develop an accountability matrix, and assign program roles and responsibilities
C.
Generate a supplier management plan to identify external stakeholders
Answers
C.
Generate a supplier management plan to identify external stakeholders
D.
Create a communications management plan, and establish reporting formats
Answers
D.
Create a communications management plan, and establish reporting formats
Suggested answer: A