Question 313 - PgMP discussion
An organization must accelerate a product to market. The program manager completes the preliminary program steps and holds a kick-off meeting. Project managers submit their preliminary schedules for review.
What should the program manager do next?
A.
Assign resources to the schedule and report the revised delivery date to the project managers.
B.
Work with the project managers to refine the project schedules and deliverables to align with the program milestones.
C.
Revise the project schedules to meet the program schedule and communicate to stakeholders.
D.
Integrate the project schedules into the program schedule and report the revised delivery date to the project managers