List of questions
Related questions
Question 315 - PgMP discussion
Stakeholders ask the program manager to assess reasons for the project's delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.
The program manager distributes information in accordance with which of the following?
A.
Stakeholder engagement plan
B.
Program governance charter
C.
Schedule management plan
D.
Communications management plan
Your answer:
0 comments
Sorted by
Leave a comment first