A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?

A.
Estimate the project team's capacity.
Answers
A.
Estimate the project team's capacity.
B.
Determine how much work can be delivered.
Answers
B.
Determine how much work can be delivered.
C.
Calculate how much work will fit into the next iteration.
Answers
C.
Calculate how much work will fit into the next iteration.
D.
Estimate items in the product backlog.
Answers
D.
Estimate items in the product backlog.
Suggested answer: A