An agile team is preparing a release plan for a project. What information will the team need to complete this plan?
A.
Amount of work needed to complete a single user story
B.
Amount of work that can be accomplished by each team member
C.
Amount of work that can be accomplished in an iteration
D.
Amount of work that can be accomplished by the entire team