List of questions
Related questions
Question 67 - PMI-ACP discussion
A mature agile team welcomes a new member. Due to poor experiences with a previous team, the new member is reluctant to communicate.
What should the agile project leader do?
A.
Bring up the new member's impediments at the next meeting to demonstrate team support of input.
B.
Assure the new member that inputs on impediments are valued, and demonstrate this at the next meeting.
C.
Have a senior lead work with the new member to avoid a negative impact on team productivity.
D.
Privately work with the new member to address any impediments.
Your answer: