Question 6 - PMI-ACP discussion
The agile practitioner has determined that two different team members are working on addressing the same major issue on the project. How should the agile practitioner address this?
A.
Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.
B.
Add the issue to the kanban board and assign the it to the team member who has made the most progress on resolving it.
C.
Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.
D.
Document all project issues in a common space and ask the team members to decide on task allocation principles.