Question 31

Report
Export
Collapse

During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?

Rework the iteration scope to accommodate these requirements.
Rework the iteration scope to accommodate these requirements.
Add these requirements into the product backlog for future consideration.
Add these requirements into the product backlog for future consideration.
Raise the discovery of these requirements as an issue, and escalate to management.
Raise the discovery of these requirements as an issue, and escalate to management.
Immediately start working on these requirements.
Immediately start working on these requirements.
Suggested answer: B
asked 23/09/2024
David Llamas Ampudia
32 questions

Question 32

Report
Export
Collapse

The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

Commit to a specific feature set for delivery.
Commit to a specific feature set for delivery.
Explain that a commitment will be provided after planning.
Explain that a commitment will be provided after planning.
Have the team estimate in story points to commit to a specific set of features.
Have the team estimate in story points to commit to a specific set of features.
Use the team's historical velocity to calculate a range of features that can be delivered.
Use the team's historical velocity to calculate a range of features that can be delivered.
Suggested answer: D
asked 23/09/2024
Anass Chadid ansari
38 questions

Question 33

Report
Export
Collapse

An agile team has been in place for five years and the customer is satisfied with the team's performance and deliverables. Now that the product is built and delivered, the customer is considering the future role of the Scrum Master.

What should the customer do?

Expand the Scrum Master's role to other projects, while allowing them to support the current project.
Expand the Scrum Master's role to other projects, while allowing them to support the current project.
Release the Scrum Master, since the team is adequately skilled with agile practices.
Release the Scrum Master, since the team is adequately skilled with agile practices.
Expand the product owner's role to serve as the Scrum Master, while providing additional product knowledge.
Expand the product owner's role to serve as the Scrum Master, while providing additional product knowledge.
Increase the functional manager's role to act as the Scrum Master, while providing additional information about functional areas.
Increase the functional manager's role to act as the Scrum Master, while providing additional information about functional areas.
Suggested answer: D
asked 23/09/2024
Sorin Craia
39 questions

Question 34

Report
Export
Collapse

A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup.

What should the Scrum Master do?

Ask the product owner how upper management's comments can be redirected.
Ask the product owner how upper management's comments can be redirected.
Direct the developer team to ignore the phone calls and emails.
Direct the developer team to ignore the phone calls and emails.
Ask the product owner to enter the requests into the product backlog as high priority.
Ask the product owner to enter the requests into the product backlog as high priority.
Personally respond to upper management's phone calls and emails.
Personally respond to upper management's phone calls and emails.
Suggested answer: A
asked 23/09/2024
Mohammed Hamid
46 questions

Question 35

Report
Export
Collapse

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface.

What should the team have done to improve retrospective outcomes?

Invited subject matter experts (SMEs)
Invited subject matter experts (SMEs)
Conducted problem detection to determine root causes
Conducted problem detection to determine root causes
Measured and reported the outcome of improvement actions to the team
Measured and reported the outcome of improvement actions to the team
Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration
Kept track of all current issues in a log, and then reviewed their progress at the end of every iteration
Suggested answer: A
asked 23/09/2024
Christina Chelioti
36 questions

Question 36

Report
Export
Collapse

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

Notify the product owner and begin resolution.
Notify the product owner and begin resolution.
Communicate the issue to the team in the next stand up meeting.
Communicate the issue to the team in the next stand up meeting.
Immediately begin resolution, and communicate it to the team during the retrospective.
Immediately begin resolution, and communicate it to the team during the retrospective.
Work on the next activity, and communicate it to the team during the retrospective.
Work on the next activity, and communicate it to the team during the retrospective.
Suggested answer: C
asked 23/09/2024
Naing Thet
41 questions

Question 37

Report
Export
Collapse

What should the agile practitioner know about tracking velocity?

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
Suggested answer: C
asked 23/09/2024
Jessica Redmond
30 questions

Question 38

Report
Export
Collapse

After seeing the planned features for an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity.

How can this issue be resolved?

Break down the feature into smaller parts, and commit to completing the minimum viable product.
Break down the feature into smaller parts, and commit to completing the minimum viable product.
Complete the iteration to which they have already committed, and include the feature in the next release.
Complete the iteration to which they have already committed, and include the feature in the next release.
Change the planned features to include only the vitally important one.
Change the planned features to include only the vitally important one.
Extend the iteration to complete the feature.
Extend the iteration to complete the feature.
Suggested answer: A
asked 23/09/2024
Silfredo Jimenez Munoz
35 questions

Question 39

Report
Export
Collapse

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.
Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.
Establish and keep an active risk register based on qualitative risk analysis and expected losses.
Establish and keep an active risk register based on qualitative risk analysis and expected losses.
Have each development team post the highest risk development items on the information radiator.
Have each development team post the highest risk development items on the information radiator.
Avoid risk by splitting development teams into two locations to ensure knowledge continuity.
Avoid risk by splitting development teams into two locations to ensure knowledge continuity.
Suggested answer: A
asked 23/09/2024
Cynthia Gutknecht
46 questions

Question 40

Report
Export
Collapse

As user stories are developed, what should be done to record and update acceptance criteria?

Add more user stories.
Add more user stories.
Use sprint retrospectives.
Use sprint retrospectives.
Update current user stories.
Update current user stories.
Update new tasks in the project plan.
Update new tasks in the project plan.
Suggested answer: A