PMI PMI-ACP Practice Test - Questions Answers, Page 6
List of questions
Question 51
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Agile team A struggles to deliver committed stories due to technical dependencies with team B, which continuously fails to meet its delivery commitments. What should the agile team lead do?
Question 52
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?
Question 53
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?
Question 54
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?
Question 55
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.
What steps should the project leader take to improve knowledge sharing?
Question 56
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?
Question 57
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A seven-member agile team's composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?
Question 58
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?
Question 59
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?
Question 60
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
Question