PMI PMI-ACP Practice Test - Questions Answers, Page 11
List of questions
Related questions
A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?
What can a team use to prioritize stories?
A senior team member feels underutilized. What should the agile practitioner do?
Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?
A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team.
What should the team do next?
An agile team has only one database administrator with the necessary knowledge of databaserelated tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?
A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high. When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
Question