Question 4 - PMI-ACP discussion
A product owner adds a 21-point. high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?
A.
Advise the product owner that the story will have to wait until the next sprint.
B.
Work extra hours to complete the story and satisfy the customer's requirements.
C.
Break down the story into smaller increments and negotiate other stories on the sprint backlog.
D.
Increase the length of the sprint to accommodate the story.
Your answer: