A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities. What should the agile project manager do?

A.
Provide both project teams with the highest priority needs.
Answers
A.
Provide both project teams with the highest priority needs.
B.
Request the project teams' questions in writing prior to the next meeting.
Answers
B.
Request the project teams' questions in writing prior to the next meeting.
C.
Facilitate a meeting with each team and the product owner to find a solution.
Answers
C.
Facilitate a meeting with each team and the product owner to find a solution.
D.
Provide both teams with each project's documentation.
Answers
D.
Provide both teams with each project's documentation.
Suggested answer: C