A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers.
This has created a bottleneck in completing stories.
What should be proposed to the team?
A.
Have other team developers attend training to learn database skills.
B.
Monitor the retrospectives of two additional sprints before taking action.
C.
Plan fewer stories for the sprint to reduce the database engineers' workload.
D.
Ask the scrum master to work with the product owner to remove backlog stories that have database dependency.