Question 23 - PMI-ACP discussion
An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it.
What should the agile team do next?
A.
Ensure that the product owner reviews the acceptance criteria for delivered user stories.
B.
Augment the quality assurance and continuous integration processes for delivery.
C.
Approach the relevant developers and testers regarding quality issues in upcoming iterations.
D.
Ask the product owner to define the entire scope of delivery two to three iterations in advance.