A new product owner needs to manage the backlog of a high-visibility, fast-moving project that is consuming a considerable amount of time. What should the product owner do?
A.
Schedule regular meetings with the scrum team to write, groom, and size user stories.
B.
Focus on stories based on the highest number of story points to first address those items with the highest value.
C.
Seek regular input from project stakeholders, and reflect this input in the backlog's priorities.
D.
Schedule in-person, monthly meetings with key stakeholders to review the project's progress.