During an iteration planning meeting, the team suggests changes to add product value that will require extra work and impact the schedule. What should the agile project leader do?
A.
Re-estimate the project.
B.
Finish the product as it was initially planned.
C.
Try to include as many changes as possible.
D.
Ask the product owner for approval to proceed.