The scrum master for a large project must provide an estimate of what can be delivered in six months. What should the scrum master do?

A.
Commit to a specific feature set for delivery.
Answers
A.
Commit to a specific feature set for delivery.
B.
Explain that a commitment will be provided after planning.
Answers
B.
Explain that a commitment will be provided after planning.
C.
Have the team estimate in story points to commit to a specific set of features.
Answers
C.
Have the team estimate in story points to commit to a specific set of features.
D.
Use the team's historical velocity to calculate a range of features that can be delivered.
Answers
D.
Use the team's historical velocity to calculate a range of features that can be delivered.
Suggested answer: D