Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective. What should the agile practitioner do?

A.
Review established ground rules with the team.
Answers
A.
Review established ground rules with the team.
B.
Ask team members specific questions to identify the cause.
Answers
B.
Ask team members specific questions to identify the cause.
C.
Encourage the team to continue working to maintain the iteration's schedule.
Answers
C.
Encourage the team to continue working to maintain the iteration's schedule.
D.
Meet with the product owner and stakeholders to discuss the issue.
Answers
D.
Meet with the product owner and stakeholders to discuss the issue.
Suggested answer: A