Question 50 - PMI-ACP discussion
An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?
A.
Coach the product owner to update only the acceptance criteria.
B.
Instruct the agile team to fix the user stories during the next retrospective.
C.
Facilitate a user story workshop with the agile team.
D.
Inform the product owner's manager that the work items provide insufficient detail.