List of questions
Related questions
Question 52 - PMI-ACP discussion
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?
A.
Team B has underestimated scope compared to team A.
B.
Team A is more confident in delivering velocity than team B.
C.
Both teams need to indicate their proposed technology before the estimates can be analyzed.
D.
Both teams have estimated the project to be of same size.
Your answer:
0 comments
Sorted by
Leave a comment first