Question 60 - PMI-ACP discussion
An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?
A.
Add a goal to the current iteration to fully mitigate or control the risk.
B.
Balance risk reduction and value adding activities in the next iteration.
C.
Continue with the current plan to maintain team velocity.
D.
Update the risk register and seek direction from a risk specialist.