Question 62 - PMI-ACP discussion
A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?
A.
Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting.
B.
Reprioritize backlog items to future iterations.
C.
Work with the team to deploy the first half of the backlog to ensure that value is realized.
D.
Meet with project stakeholders to review the backlog and determine if the scope should be adjusted.