An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?
A.
Conduct a requirements gathering workshop.
B.
Deliver the basic requirements iteratively.
C.
Have the product owner fill out the requirements backlog.
D.
Have the stakeholders fill out the backlog before starting the project.